Mastering Groundworks: Navigating Challenges on Occupied Construction Sites
October 25, 2024
Ysgol Ifor Bach Expansion – New Modular Teaching Facility 
November 21, 2024

New Modular Childcare Unit Extension for Cwrt Rawlin Primary School

Shanco recently partnered with long-term client Elite Systems to support an exciting modular expansion project for Cwrt Rawlin Primary School. This project involved delivering a new modular childcare unit to extend teaching space and enhance facilities for students and staff alike. Our expertise in groundworks and dedication to safety ensured that all work was completed smoothly and safely, even within a live school environment.

The Project

The project focused on the installation of a modular childcare unit, which would add valuable teaching and childcare space to the existing school. In addition to laying the groundwork for the modular building, our team was responsible for drainage modifications, pathway formation, car park reconfiguration, and soft landscaping around the site.

The Challenge

Due to the school’s sloped landscape, we faced challenges with both foundation work and drainage. The foundations required a multi-level approach to accommodate the slope, and rerouting the existing drainage systems presented additional complexity. Working in an active school environment, we also needed to uphold stringent safety standards and operational measures to ensure minimal disruption to students, staff, and daily activities.

The Approach

Our team began by addressing the site’s unique sloping terrain. We implemented pad foundations at varying levels to ensure stability, followed by the construction of blockwork piers to support the modular unit. To handle drainage, we rerouted existing systems around the building’s footprint, managing significant depths in some areas to ensure alignment with live public sewer connections under necessary licences. In the live school setting, safety was our top priority: exclusion zones, secure fencing, and scheduling around peak times helped maintain safe operations with minimal disruption.

The Results

Our team began by addressing the site’s unique sloping terrain. We implemented pad foundations at varying levels to ensure stability, followed by the construction of blockwork piers to support the modular unit. To handle drainage, we rerouted existing systems around the building’s footprint, managing significant depths in some areas to ensure alignment with live public sewer connections under necessary licences. In the live school setting, safety was our top priority: exclusion zones, secure fencing, and scheduling around peak times helped maintain safe operations with minimal disruption.

After working with Shanco on the last 4 projects I’ve found them to be an asset to my projects, truly helpful in everything they do. They work smart and stay professional throughout all tasks we’ve set, they find solutions quickly so the process is smooth.

Thank you Shanco, you’ve made my job a pleasure on these projects. I look forward to working with you again on future projects. A+++

Stephen Fleming, Contracts Manager, Elite Systems (GB) Ltd

Discover more about our commitment to excellence and our comprehensive groundworks services at Shanco. Together, let’s build the foundation for success.

End
New Modular Childcare Unit Extension for Cwrt Rawlin Primary School
This website uses cookies to improve your experience. By using this website you agree to our Privacy Policy.
Read more